2019 Road project status updates
District 1 project map
District 2 project map
District 3 project map
Magnesium chloride applications
Please do not park any vehicles along the roads during chip seal or asphalt applications.
District 1
CR 100 Catherine Store Road

This project will extend for a distance of 3.5 miles starting on the south side of Highway 82 to the City Limits of Carbondale. Preparations for this project will include pulling ditches, jetting culverts and crack sealing. This road will receive a 3/8th inch chip seal overlay. All prep and overlay should be completed by June 30th, 2019.
CR 132 – Mitchell Creek Road

This project will extend for a distance of 1.3 miles starting State Highway 6 to the Fish Hatchery. Preparations for this project will include pulling ditches, jetting and replacing culverts as needed. This road will receive a 2 inch asphalt gravel shouldering. All prep and paving should be completed by July 31, 2019.
District 2
CR 263 – Ware Lane

This project will extend for a distance of .3 miles, starting at Highway 6 to the intersection of CR 214 – Peach Valley Rd. Preparations for this road will consist of pulling ditches, replacement of culverts, tree removal, and replacement of wire fence. The road will receive a 2 inch asphalt mat and ¾†gravel shoulders. All prep and paving should be completed by July 31, 2019.
CR 233 – Peterson Lane

This project will extend for a distance of 1.4 miles, starting at Highway 6 and running to CR 233, Silt Mesa Road. Preparations for this road will consist of pulling ditches, jetting culverts, crack sealing, hot patch and soft spot repairs. The road will receive 3/8th inch chip followed by fog seal. All prep and overlay should be completed by June 30th, 2019.
CR 227 – Miller Lane

This project will extend for a distance of 1.1 miles, starting at Highway 6 and ending at CR 233, Silt Mesa Road. Preparations for this road will consist of pulling ditches, jetting culverts and crack sealing. This road will receive 3/8th inch chip followed by fog seal. All prep and overlay should be completed by June 30th, 2019.
CR 251 – Hasse Lane

This project will extend for a distance of 1 miles, starting at State Highway 325 to end of existing pavement. Preparations for this road will consist of pulling ditches, jetting culverts and crack sealing. This road will receive 3/8th inch chip followed by fog seal. All prep and overlay should be completed by June 30th, 2019.
CR 257 – Mesa Drive

This project will extend for a distance of 1 miles, starting at State Highway 325 to the cul-de-sac. Preparations for this road will consist of pulling ditches, jetting culverts and crack sealing. This road will receive 3/4th inch followed by 3/8th inch chip followed by fog seal. All prep and overlay should be completed by June 30th, 2019.
CR 291 – Stephens Hill

This project will extend for a distance of .6 miles, starting at State Highway 13 and ending at the Y intersection. Preparations for this road will consist of crack sealing. This road will receive 3/8th inch chip followed by fog seal. All prep and overlay should be completed by June 30th, 2019.
CR 252 – West Rifle Creek and CR 219 – Middle Rifle Creek

This project will extend for a distance of 2.6 miles- (2.1 miles of CR 252 and .5 miles of CR 219), starting at State Highway 325 to the end of CR 219. Preparations for these roads will consist of pulling ditches, jetting culverts and crack sealing. This road will receive 3/8th inch chip followed by fog seal. All prep and overlay should be completed by June 30th, 2019.
CR 235 – Davis Point Road

This project will extend for a distance of .7 miles, starting at Highway 6 and ending at CR 233, Silt Mesa Road. Preparations for this road will consist of pulling ditches, jetting culverts and crack sealing. This road will receive 3/8th inch chip followed by fog seal. All prep and overlay should be completed by June 30th, 2019.
District 3
CR 300 – Stone Quarry Road (Una)

This project will extend for a distance of 4.7 miles, starting at the bottom of RV Park Hill to the train tracks. Preparations for this road will consist of pulling ditches and cleaning and replacing culverts, as needed. This road will receive 4 miles of 2 inch asphalt mat and .7 miles of 4 inch gravel and 4 inch asphalt mat. All prep and paving should be completed by July 31, 2019.
CR 319 – West Mamm

This project will extend for a distance of 7 miles, starting at the intersection of CR 352 (Airport Road) to the end of the pavement. Preparations will consist of cleaning ditches, checking and jetting culverts, pull shoulders as needed. This road will receive 3/8th inch chip followed by fog seal. All prep and overlay work should be completed by June 30th, 2019.
CR 352 – Airport Road

This project will extend for a distance of 2.8 miles, starting at the Rifle City Limits to the intersection of CR 315. Preparations will consist of cleaning ditches, checking and jetting culverts, pull shoulders as needed. This road will receive 3/8th inch chip followed by fog seal. All prep and overlay work should be completed by June 30th, 2019.