2014 Road project status updates
District 1 project map
District 2 project map
District 3 project map
Battlement Mesa
Project overview information
Magnesium chloride applications
Please do not park any vehicles along the roads during chip-seal or asphalt applications.
District 1
CR 103 – Crystal Springs road
Paving is done, shoulder work to be completed 7/15-7/18
Paving is scheduled to start Monday June 30th on County Roads 100 and 103.
This project will begin just north of Hwy 82 and extend for 4 miles to the intersection of CR 100. It will include .9 miles of CR 100 ending at the intersection with CR 113. A 2” asphalt overlay will be placed to re-establish water drainage off the road improve surface conditions. Preparation activities will include cleaning ditches, culverts and any necessary shoulder work.
- Preparation Activities: Week of April 21, 2014
- Estimated duration: 4 days
- Resurfacing by Contractor: TBA
- Estimated duration: TBA
- Expected Delays: Minimal
- Alternate Route: SE on CR 100 to Hwy 82; SW on CR 113 to Hwy 82
CR 293 – North Graham
5/21/14 – Paving on CR’s 293 and 294 is starting today.
This project will begin at the “Y” intersection where both roads meet. It will extend SW on CR 294 for .4 miles and north on CR 293 for .6 miles ending at the Rifle City Limits. A 2” asphalt overlay will be placed to re-establish water drainage and improve surface conditions. Preparation activities will include cleaning ditches and culverts along with any necessary shoulder work.
- Preparation Activities: TBA
- Estimated duration: TBA
- Resurfacing by Contractor: TBA
- Estimated duration:
- Expected Delays: Minimal
- Alternate Route: W on 16th St. to Railroad Ave; or W on Third St. to Whiteriver Ave.
CR 294 – S Graham road
5/21/14 – Paving on CR’s 293 and 294 is starting today.
This project will begin at the “Y” intersection where both roads meet. It will extend SW on CR 294 for .4 miles and north on CR 293 for .6 miles ending at the Rifle City Limits. A 2” asphalt overlay will be placed to re-establish water drainage and improve surface conditions. Preparation activities will include cleaning ditches and culverts along with any necessary shoulder work.
- Preparation Activities: TBA
- Estimated duration: TBA
- Resurfacing by Contractor: TBA
- Estimated duration:
- Expected Delays: Minimal
- Alternate Route: W on 16th St. to Railroad Ave; or W on Third St. to Whiteriver Ave.
CR 312 – Garfield Creek road
Garfield Creek – Paving start date is schedule for 8/18
Garfield Creek will begin at the intersection of CR 335 and extend south for 8 miles. The road will be milled and gravel will be added before a 4” asphalt overlay will be placed. Preparation activities will include culvert cleaning, extensions and/or replacements as needed. There will also be ditch cleaning and shoulder work activities.
- Preparation Activities: Week of April 14, 2014
- Estimated duration: 2 weeks
- Resurfacing by Contractor: TBA
- Estimated duration: TBA
- Expected Delays: Minimal
- Alternate Route: There is no alternate route, please watch for road crews and plan for timing and safety.
CR 314 – Alkali Creek
Chip sweeping and fog seal to take place 7/15 – 7/18
Chipseal will begin on CR 314- Alkali Creek and Mountain Shadows Subdivision on Wednesday July 9th.
Paving has taken place, Chipseal is still pending. Driveway aprons will be taken care of after chipseal has been completed.
- Expected Delays: Minimal
- Alternate Route: There is no alternate route, please watch for road crews and plan for timing and safety.
Mountain Shadows Subdivision
CR 462, 463, 464, 465, and 467 Apricot Circle, Cherry Ct., Peach Ct., Pear Ct., and Plum Ct.
Chip sweeping and fog seal to take place 7/15 – 7/18
Paving has taken place, Chipseal is still pending. Driveway aprons will be taken care of after chipseal has been completed.
- Expected Delays: Minimal
- Alternate Route: There is no alternate route, please watch for road crews and plan for timing and safety.