Planned road projects


District 1 project map
     |      District 2 project map     |      District 3 project map / Battlement Mesa

 |     Project overview information     |

Guardrail installation is completed

Also, County Roads 109, 115, 121,137, 151, 168, 250, 261 and 311 are still in the engineering phase for future improvements, so are not listed below.
Guardrail Project Maps

Please do not park any vehicles along the roads during chip-seal or asphalt applications.

District 1
  County Roads 55, 57, 59 - Glenwood Avenue, Sopris Avenue, Pine Street  
County Road 55 CR 55, 57, 59

County Road 55

previous view

traffic cone
100% complete

chip-seal application - project completed.

     
  County Roads 69, 70, 71 & 72 - Westbank Road, Oak Lane, Fairway Lane, Meadow Lane  
County Road 69 Westbank County road 69
previous view
traffic cone
100% complete

Upgrade from chip seal to asphalt application - project completed.
 
     
  County Road 106 - Satank Road  
County Road 106 CR 106

County Road 106
previous view

traffic cone
100% complete

chip-seal and fog seal application - project completed.
     
  County Road 112 - Crystal Springs Mtn. Road  
County Road 112 CR 112 County Road 112
previous view
traffic cone
100% complete

chip-seal application - project completed.
     
  County Road 114 - CMC Road  

Leveling course with a 3” asphalt overlay from Highway 82 to Pinion Pines.

County road 114
previous view
CR 114
traffic cone
100% complete
Asphalt overlay - completed
Estimated start date: Paint striping will take place at the end of August.
Estimated duration: 1 day
Delays: none
     
  County Road 127 - Three Mile Road  
County Road 127 CR 127 County Road 127
previous view
traffic cone
100% complete

 

Slope stabilization and paving.
 
     
  County Road 161 - Kings Row  
County Road 161 CR 161 County road 161
previous view
traffic cone
100% complete

chip-seal and fog seal application - project completed.

     
  County Road 161A - Prince Drive  
Country Road 161A CR-161A County Road 161A
larger image
traffic cone
100% complete

chip-seal and fog seal application - project completed.

     
  County Road 190 - Lions Ridge Road  
County Road 190 CR-190 County road 190
larger image
traffic cone
100% complete

chip-seal and fog seal application - project completed.

     
  County Road 221 - Green Lane  
County Road 221 County Road 221
100% complete
traffic cone

chip-seal application: completed
Fog seal application: completed

larger image
     
  County Road 227 - Miller Lane  
County Road 227 Leveling and chip seal application227 County Road 227
100% complete
traffic cone

chip-seal application: completed
Fog seal application: completed

larger image
     
  County Road 231 - 1st Street  
County Road 231

Levelled and asphalt applied, paving done, still doing shoulder work - applying two feet of gravel to the sides of the road.

cr-231

County Road 231
100% complete
traffic cone

Asphalt overlay: completed
Estimated start date: completed

larger image
     
  County Road 240 - Bruce Road  
County Road 240 Asphalt application

cr240
County Road 240
100% complete
traffic cone

Asphalt overlay
Estimated start date: Early August
Estimated duration: 2 days
Delays: minimal

larger image
     
  County Road 246A - Landfill Road  
County Road 246A This road will have 4" of asphalt applied in several layers to level the road for a more permanent surface.

cr246
County Road 246A
100% complete
traffic cone

Asphalt overlay
Estimated start date: Late July
Estimated duration: 2 days
Delays: minimal

larger imageCounty Road 250
     
  County Road 250 - Bendetti Lane  
County Road 250  
100% complete
traffic cone

Asphalt Overlay: completed
Estimated start date: Early August
Estimated duration: 2-3 days
Delays: minimal

larger image
     
  County Road 266 - Asgard Subdivision  
County Road 266 266 County Road 266
100% complete
traffic cone

chip-seal application:completed
Fog seal application: completed

larger image
     
  County Road 502 - Peach Lane  
County Road 502 Peach Lane  
traffic cone
100% complete

Asphalt application
 
     
  County Road 310  
County road 310 Westbank County road 69
previous view
traffic cone
100% complete

Gravel haul: completed
Asphalt overlay: completed 
Shoulder work: completed
 
     
  County Road 311 - Divide Creek Road  
County road 311 sign Paving with 4" mat, 1,000 feet of guardrail. Future guard rail installation and capital infrastructure engineering is underway.

cr311
County road 311
 
100% complete
larger image
 

Asphalt overlay
Estimated start date: to be determined
Estimated duration: to be determined
Delays: minimal

 
     
  County Road 324 - Maxfield Road  
County road 324 sign 324paved

Country road 327
previous view
100% complete
traffic cone

Asphalt overlay
Estimated start date: August 7-8
Estimated duration: 2 days
Delays: minimal

 
     
  County Road 327 - Halls Gulch  
County road 327 sign 327paved County road 324
previous view
100% complete
traffic cone Asphalt overlay: Estimate July 30
Milling/Gravel: July 23 - July 27
Estimated duration: 1.5 weeks
Delays: minimal
 
     
  County Road 337  
County Road 337 Westbank County road 69
previous view
traffic cone
100% complete

Gravel haul: completed
Asphalt overlay: completed
Shouldering: completed

 
     
  County Road 338 - Battlement Creek Road  
Country road 338 Westbank County road 338
previous view
traffic cone
100% complete

Gravel Haul: completed
Asphalt Overlay: completed
Shouldering: completed

     
County Road 340 County Road 340 County Road 340
previous view
Westbank
traffic cone
100% complete

Gravel Haul: completed
Asphalt Overlay: completed
Shouldering: completed

 
     
  County Road 342 - Fairview Road  
County road 342 Asphalt paving. Replace four culverts, add culvert extensions

cr342
County road 342
100% complete
traffic cone

Asphalt overlay
Estimated start date: Mid August
Estimated duration: 2-3 days
Delays: minimal

larger image
     
County road 355 County Road 355

County road 355

previous view
Westbank
traffic cone
100% complete

Gravel haul: completed
Asphalt overlay: completed
Shouldering: completed

 
     
  Battlement Mesa chip seal and fog
  Aspen Way, Boulder Ridge Drive, Eagle Rock Place, Fairway Drive, Hackberry Lane, Holly Way, Iron Wedge Circle, Meadow Creek Court, Mesa Vista Place, Pine Tree Place, Ponderosa Circle, Rainbow Court, Rampart Place, Roan Creek Place, Silver Plume Drive, Smokey Hill Court, Spruce Court, Tamarisk Court, Valley View Place  
  chip-seal application battlement mesa map
100% complete
chip-seal application: completed
Sweep/Fog seal application: Week of 7/30 - 8/1
Estimated duration: 1 day
Delays: minimal
Please Do Not Park Your Vehicle On The Street During These Dates!
    larger image
 
 
 
Road & Bridge Administration
District 2-3 facility
0298 County Road 333A
Rifle, CO 81650
Email Road & Bridge


970-625-8601 | phone
970-625-8627 | fax
  Road & Bridge
District 1 facility
7300 Highway 82
Glenwood Springs, CO 81601
Email Road & Bridge


970 945-1223 | phone
970-945-1318 | fax
   
 
privacy policy